Tuesday, April 12, 2011

Construction Updates

As of today, April 12th, the project is officially listed as 41% complete.  Pending some questions to be resolved with the fire alarm, turn over of the stairwells will probably not occur until right after Easter while other work on the restrooms and third floor continue as planned.

The handicap ramp in the back will be next and the dock is expected to be able to return to normal operations in the first or second week of May.  An official notification will be sent out when ready.  Project completion is now projected to be end of June, early July.

Some of you might be interested to know that of the materials removed from the building so far as part of demo or replacement, 83% has been diverted from the landfill either through reuse or recycle.

So, so far so good, next update will probably not be until next week.