Later this week we will be switching stairwells and that is the final piece of demo that needs to occur. More information will be posted on Jackson-l regarding pathways and access later this week. For now, here is a look at the projects progress:
This is the new windows on the third floor with the blackout feature. These windows will also be hidden in the stacks area to minimize exposure to light.
This is how they look from the outside:
This is the window in one of the staff offices being replaced. This are clear but will not open to maintain the environmental controls being established on the third floor:
This is the ventilation system on the third floor which has created a lot of the noise lately. They are almost done:
This is a look at the sprinkler system going in on the third floor including a view of the IT network ladder that supports the data wiring:
Restroom update; sinks are in both men's and women's, next week there will be some more drilling to create the path for the exhaust fans. Wonder how we are going to determine who gets to "go" first?