Renovation Status

I wanted to update you on the status of our project, with the noisy and dusty part done it is hard to realize that work is still being done, but I can assure your that it is.  The aforementioned punch list is getting near completion, there are several important items to still address before the inspection process is started.  But some finishing touches are going up:
And there is even action at the restrooms:

Meanwhile we are making local adjustments where we can, such as the second floor conference room is finished off and larger..............


Next Saturday we are expecting to do the building power shut down test, early before we open.  This means the power to the building will be shut down in order to test fire alarms and batteries.  Please do not plan for any other activities on this morning.  This activity should be completed by 9:30 AM.

Once this is done and passes, the expectation is that the inspection can be scheduled.  Because this is still later than we anticipated we are expecting to not have total access to space in Hodges until later in the month.  Please continue to seek alternative venues as needed. 

Have a great holiday weekend and I'll update more as we progress closer to the end.
mc