Or at least knocked down and piled up!  This week the crew has completed most of the demo in ERIT as demonstrated below:
They are staging the debris in order to hand carry out next week.  The plan next week is to carry out the demo'd materials and carry in new materials needed for rebuilding.  They will be taking advantage of spring break and will do this using the wider marble monument stairs next to the College Ave. entrance.
So, please avoid those stairs yourself next week in order to accommodate this activity related to the project.