Wednesday, June 15, 2011

Construction Meeting Update for June 14th

Yesterday was a monthly construction update meeting with all parties including state construction.  The following is a recap of the meeting:
  • the project is 78% complete, with demo considered 100% complete
  • 79% of demo'd material has been recycled
  • in-wall inspections on the framing for the south stairwell has been completed and drywall installation will occur next

  • Exterior ramp is now complete.




Expected time-line:
  • South stairwell and restrooms have another 2 to 3 week window for completions, inspections and beneficial occupancy
  • Third floor occupancy will be somewhat delayed as the HVAC system is now expected to need extra time for system control set-up and environmental regulation.
Overall, end of all renovation work is now projected to be closer to the end of July.