- the project is 78% complete, with demo considered 100% complete
- 79% of demo'd material has been recycled
- in-wall inspections on the framing for the south stairwell has been completed and drywall installation will occur next
- Exterior ramp is now complete.
Expected time-line:
- South stairwell and restrooms have another 2 to 3 week window for completions, inspections and beneficial occupancy
- Third floor occupancy will be somewhat delayed as the HVAC system is now expected to need extra time for system control set-up and environmental regulation.
mc