Wednesday, June 8, 2011

Second Floor Demo

This week the last of the "messiness" occurs with the second floor demo.  They are having to work around the IT network array which is between the corridor and the conference room:




And remember that corner gets relocated in the corridor going toward admin:

While this is happening, the new walls are going up on the first floor to shape that fire passage.
 Notes from yesterday's construction meeting:

  • the new HVAC unit for the third floor is expected to be installed somewhere around June 20th.
  • sprinkler system is in on the third floor and once the duct work is done the lights and ceiling tiles will go in.  We walked the shelving plan expected to be installed in the closed stack area and measured ceiling heights etc.  Looks good!
  • Bathrooms are missing a couple of parts need to complete, once received the rest will be put together.
  • Timeline on project stills gives us a few more weeks, let's say 4 to 5 at this stage, but all major questions and concerns have been addressed, so we are confident the end is near!